The Consultant has prepared the contract documents, including the Advertisement for Bids. Staff has reviewed the documents and find them to be acceptable.
Project Funding
This maintenance project has been planned for through the Capital Improvement Program. The project is budgeted to be funded through the water utility fund.
Schedule
Advertise for Bids January 24 & 31, 2019
Bid Opening February 14, 2019
Award Construction Contract February 25, 2019
Antenna Removal and Relocation April/May 2019
Construction Start June 3, 2019
Construction Substantial Completion October 5, 2019
Construction Final Completion October 31, 2019